Connecticut DOT Road Work, Route 30 In South Windsor

You may be wondering what the DOT is doing on Rt 30 from the 4 Corners to RT 5… I received the DOT plan for the resurfacing of RT 30 and it’s worth reading. Please plan ahead and avoid the traffic jams that may happen during this work.

– Milling and Resurfacing Project, Route 30 in South Windsor –

The Connecticut Department of Transportation is announcing that a milling and resurfacing project will be performed on Route 30 in South Windsor, beginning Monday, August 20, 2018.

The project consists of milling and resurfacing a 3.95 mile segment of Route 30 in South Windsor. The milling portion of this project is scheduled to begin on Monday, August 20, 2018 to Friday, August 31, 2018. The resurfacing segment of this project is anticipated to begin on Wednesday, September 5, 2018 to Tuesday, September 18, 2018.

This project is included in the Department of Transportation’s 2018 Vendor Resurfacing Program.

– LANE CLOSURE INFO –

Motorists can expect lane closures on Route 30 in South Windsor from US Route 5 to Route 194. Traffic control personnel and signing patterns will be utilized to guide motorists through the work zone. The regular work schedule for this project is 6:00 a.m. to 3:00 p.m. (Monday – Friday). Work will begin on the first day of milling and paving at 5:00 a.m.

Motorists should be aware that modifications or extensions to this schedule may become necessary due to weather delays or other unforeseen conditions. Motorists are advised to maintain a safe speed when driving in this vicinity.

#SouthWindsor #RoadWork #Construction